Active Construction Project Update
Contract C2106: SDHP – Water Main Project
Bid Status
Contract No.
Anticipated Construction Start Date
Estimated Completion
Project Description
The Northshore Utility District (NUD) is committed to providing safe and reliable water & sewer services to its customers. NUD actively partners with other agencies to achieve this goal and views the customer as a partner as well. We know that construction can be very disruptive and noisy; however, this is necessary to provide the best service possible for now and into the future. NUD staff appreciate your patience as we work in your area.
Asphalt grind and overlay of the areas is planned after completion of all the water installations and connections, and when weather allows. All trenches will be hot patched before the contractor moves off the site. Advanced notifications will be provided for planned outages and are not expected to last more than 6-8 hours during a single day.
Local access to driveways, emergency vehicles, garbage pickup, and mail service will be facilitated. There may be a few minutes’ delay when the equipment is directly in front of a driveway, so please allow extra time in your travel schedule.
WORK LOCATIONS + PROJECT UPDATES AS OF MARCH 2, 2026
Northshore Utility District (NUD) will be replacing water main and services in 7 neighborhoods within the District’s boundary.
The 7 locations are referred to by the Letter “A”, “B”, etc, and the numbers represent the streets impacted and the closest cross streets. The contractor’s schedule indicates they will go in the order below, with each neighborhood taking approximately 4-6 weeks of work. The final grind and overlay in all neighborhoods will take place in mid-late summer.
A – 190/35… Work on NE 190th Place, Lake Forest Park- Complete except for Overlay
F – 120/80…Work on 80th Place NE, Kirkland—Pipe in. Testing and Connections next
E – Juanita/88…Work on Juanita Lane, Kirkland- March, Installing pipe, testing
G – 124/106…Work on 106th Place NE, Kirkland- Start end of March or first of April
D – 145/104…Work on 104th Ave NE, Bothell- Start May/June
B – 190/60… Work on 60th Place NE, Kenmore- Start June/July
C – 198/64…. Work on 64th Ave NE, Kenmore- Start June/July
The map of locations can be seen on page 1 of the plans.
Please check back every few weeks as we update this website page. Each location is expected to take 1-2 months of work depending on length of street and number of water services.
If you have questions about this project, please contact Jamie Lamb, Construction Manager, at JLamb@nud.net or on his direct line at 425-521-3722. For all inquiries, please include the Project Name (SDHP) and your address. Your email or call will be returned as soon as possible.
Postcard notifications have been sent to E & G. The remaining areas of D, B & C will receive postcards soon.