Active Construction Project Update

Contract C2106: SDHP – Water Main Project

Bid Status

Awarded to Kar-vel Construction

Contract No.

C2106: Small Diameter High Pressure Water Main Replacement Project

Anticipated Construction Start Date

January 5th, 2026

Estimated Completion

September 30th, 2026

Project Description

The Northshore Utility District (NUD) is committed to providing safe and reliable water & sewer services to its customers.  NUD actively partners with other agencies to achieve this goal and views the customer as a partner as well.  We know that construction can be very disruptive and noisy; however, this is necessary to provide the best service possible for now and into the future.  NUD staff appreciate your patience as we work in your area.

Asphalt grind and overlay of the areas is planned after completion of all the water installations and connections, and when weather allows.   All trenches will be hot patched before the contractor moves off the site. Advanced notifications will be provided for planned outages and are not expected to last more than 6-8 hours during a single day.

Local access to driveways, emergency vehicles, garbage pickup, and mail service will be facilitated. There may be a few minutes delay when the equipment is directly in front of a driveway, so please allow extra time in your travel schedule.

WORK LOCATIONS

Northshore Utility District (NUD) will be replacing water main and services in 7 neighborhoods within the District’s boundary.

The 7 locations are referred to as “Schedules”, and the numbers represent the streets impacted and the closest cross streets.

Schedule A – 190/35……. Work on NE 190th Place, Lake Forest Park

Schedule B – 190/60……. Work on 60th Place NE, Kenmore

Schedule C – 198/64……..Work on 64th Ave NE, Kenmore

Schedule D – 145/104……Work on 104th Ave NE, Bothell

Schedule E – Juanita/88…Work on Juanita Lane, Kirkland

Schedule F – 120/80………Work on 80th Place NE, Kirkland

Schedule G – 124/106…….Work on 106th Place NE, Kirkland

The map of locations can be seen on page 1 of the plans.

PROJECT CALENDAR & UPDATES AS OF NOVEMBER 20,2025

Schedules A and F will be done first, beginning in January and February.  Once the District receives the contractor’s anticipated calendar of work at the remaining 5 locations, that information will be shared. Please check back every few weeks as we update this website page.

If you have questions about this project, please contact Jamie Lamb, Construction Manager, at JLamb@nud.net or on his direct line at 425-521-3722. For all inquiries, please include the Project Name (SDHP) and your address. Your email or call will be returned as soon as possible.

Postcard notifications coming soon.