Active Construction Project Update
Contract C2305: Water Main Replacement
Bid Status
Contract No.
Anticipated Construction Start Date
Estimated Completion
Project Description
WATER MAIN REPLACEMENT & RESTORATION
The Northshore Utility District (NUD) is committed to providing safe and reliable water & sewer services to its customers. NUD actively partners with other agencies to achieve this goal and views the customer as a partner as well. We know that construction can be very disruptive and noisy; however, this is necessary to provide the best service possible for now and into the future. NUD staff appreciate your patience as we work in your area.
The project map showing the location can be seen here.
WHAT WORK IS GOING TO HAPPEN?
Northshore Utility District (NUD) awarded a contract to B & B Utilities who will be replacing 3350 feet of water main, 97 water services, 7 fire hydrants, and replacing 35 pedestrian ramps prior to the asphalt overlay.
The final grind and asphalt overlay in all neighborhoods will take place in late fall as weather allows.
IMPACTS TO RESIDENTS
Local access to driveways, emergency vehicles, garbage pickup, and mail service will be facilitated. There may be a few minutes’ delay when the equipment is directly in front of a driveway, so please allow extra time in your travel schedule.
Advanced notifications will be provided for planned water outages and are not expected to last more than 6-8 hours during a single day. Due to timing and reconnecting the underground pipes, some customers will experience 2-3 planned outages during the project. Notice will be provided 3-5 business days in advance of the single day outages.
PROJECT SCHEDULE UPDATE AS OF MARCH 27, 2026
NE 122nd Place and NE 121st Place cul-de-sac work to begin on April 16, 2026
The contractor will be moving into the neighborhood to begin work on the northern portion of the project first, installing water main and services. A tentative schedule estimates that the water line pipe work will be completed in mid-June and the restoration, including pedestrian ramps and overlay, should be completed by end of July weather depending.
81st Ave NE, NE 121st St, and NE 120th St. work to begin around June 2026
The contractor will be moving into this area to begin the pipe installation. This area is tentatively scheduled to be completed with pipe work around September, with pedestrian ramps and overlay completion scheduled for late October dependent on weather.
The contractor is still working on specific details of the schedule. Additional information will be included on this page as it becomes available.
Please check back every few weeks as we update this website page.
If you have questions about this project, please contact Jamie Lamb, Construction Manager, at JLamb@nud.net or on his direct line at 425-521-3722. For all inquiries, please include the Project Name (C2305 or 122-84) and your address. Your email or call will be returned as soon as possible.
Postcard notifications have been sent to impacted residents and the surrounding area.