2006 Capital Improvement Program
2006 Sewer Capital Improvement Program
Program / Project

Budget

ANNUAL LIFT STATION PROGRAM
Lift Station No. 14 Rehabilitation - 2007 $1,555,000

Subtotal

$1,555,000
NEW SEWER EXTENSION PROGRAM
ULID 115 - Juanita Beach Camps Sewer Extension (District Participation Amount) - COMPLETE $250,000
126/80 Sewer Project - COMPLETE $350,000
203/88 Sewer Project - COMPLETE $202,000
128/84 Sewer Project - COMPLETE $70,000
124/86 Sewer Project - COMPLETE $90,000
178/92 Sewer Project - COMPLETE $360,000
New Extensions - Placeholder $250,000

Subtotal

$1,572,000
ANNUAL SEWER MAIN UPGRADE PROGRAM
Repair & Replacement Placeholder $442,828
Manhole Coating / Manhole Repair Project - FUTURE $150,000
Comprehensive Plan Update - COMPLETE $75,000
Subtotal $667,828
 
TOTAL SEWER PROGRAM $3,794,828

Top of Page

2006 Water Capital Improvement Program
Program / Project

Budget

NEW WATER SYSTEM IMPROVEMENTS
New Extensions - Placeholder $353,709
126/80 Water Main Extension - COMPLETE $60,000
205/61 Water Main Extension - COMPLETE $100,000

Subtotal

$513,709
WATER MAIN REPAIR & REPLACEMENT PROGRAM
Repair & Replacement Placeholder $250,000
126/80 Water Main Replacement - COMPLETE $80,000
Sound Transit Water Main Replacement - IN PROGRESS $225,000
SR 522 Water Main Replacement - IN PROGRESS $546,290
PRV Rehabilitation Project - Design - IN PROGRESS $50,000
Comprehensive Plan Update - COMPLETE $75,000

Subtotal

$1,226,290
RESERVOIR IMPROVEMENTS
Reservoir VA Improvements - IN PROGRESS $151,304
Subtotal $151,304
 
TOTAL WATER PROGRAM $1,891,303
 
TOTAL 2006 CAPITAL IMPROVEMENT PROGRAM $5,686,131