2004 Capital Improvement Program
2004 Sewer Capital Improvement Program
Program / Project

Budget

ANNUAL LIFT STATION PROGRAM
Lift Station No. 14 Rehabilitation Study - COMPLETE $50,000
Lift Stations Telemetry Upgrade $125,000

Subtotal

$175,000
NEW SEWER EXTENSION PROGRAM
Locations as Necessary $250,000
202/68 Sewer Project - COMPLETE $983,000
190/86 Sewer Project - COMPLETE $263,000
187/40 Sewer Project - COMPLETE $260,000
Consultant Design - 2005 CIP Projects $300,000

Subtotal

$2,056,000
ANNUAL SEWER MAIN UPGRADE PROGRAM
Totem Lake Sewer Improvements - COMPLETE $726,000
Kenmore - Swamp Creek Bridge Replacement - 2005 $150,000
Repair & Replacement - Placeholder $250,000
Manhole Coating Project - 2006 $150,000
Subtotal $1,276,000
 
TOTAL SEWER PROGRAM $3,507,000

Top of Page

2004 Water Capital Improvement Program
Program / Project

Budget

NEW WATER SYSTEM IMPROVEMENTS
Extensions - Placeholder $250,000

Subtotal

$250,000
WATER MAIN REPAIR & REPLACEMENT PROGRAM
NE Bothell Way Main Replacement - 2006 $580,000
128/116 Main Replacement (Sound Transit) - 2006 $225,000
Totem Lake Water Improvements - COMPLETE $603,000
Kenmore - Swamp Creek Bridge Replacement - 2005 $250,000
Consultant Design - 2005 CIP Projects $70,000
Repair & Replacement - Placeholder $250,000

Subtotal

$1,978,000
RESERVOIR IMPROVEMENTS
Westhill - Standpipe Stability Project - COMPLETE $750,000
Norway Hill Reservoir Improvement Study - COMPLETE $10,000
Subtotal $760,000
 
TOTAL WATER PROGRAM $2,988,000
 
TOTAL 2004 CAPITAL IMPROVEMENT PROGRAM $6,495,000